Water and sanitation

Year Client Project Name Location Short Description
2016-2017 Min of Water & Environment Design and project management of Water for production facilities (WFP) under the water supply and sanitation programme (WSSP) Katakwi, Otuke and Apac districts
  • Establish the existing and potential water demand for production purposes including but not limited to; domestic, agricultural, commercial and industrial.
  • Make a thorough assessment of the water resources potential in the selected areas.
  • Examine and evaluate the potential water sources identified and any other possible alternatives.
  • Identify the most appropriate technology option for developing existing water resources in order to meet water demand.
  • Undertake detailed design of the most appropriate water for production facilities for the three districts and produce detailed bills of quantities, design reports, drawings and tender documents.
  • Identify and assess optimal use of the proposed water for production facilities and its impact on production and productivity. Assess main production constraints and recommend appropriate interventions to ensure sustainability.
2016-2018 Min of Water & Environment
Contractor: Vambeco Enterprises ltd
Consultant: Alliance Consultants Ltd
Construction of Nyarwodho gravity flow scheme – Phase II Nebbi district
  • 27.4km Treated Water Transmission mains of OD 160 – 110mm uPVC pipelines with 1no. 10m3 Break-Pressure Tank.
  • Storage Pressed steel tanks at Ageno 89m3, Panyango 105m3, Pakwach (Nyabang) 131m3.
  • Distribution Mains:
    – 17.4km of Primary distribution lines in OD 40 – OD 90 HDPE and 12.1 km of OD 110 – OD 125 uPVC
    – 57km of Secondary distributions in OD 63 – OD 20 HDPE
  • Construction of Booster Pump house including 27m2 blockwork structure, 2no. 45kW pump sets with motor control centre and 10kVA backup electric generator.
  • Consumer Connections: 300no yard taps, 20no. Public stand posts and 10no. Water sales kiosks
2014-2016 Min of Water & Environment Construction of Nyarwodho Gravity Flow Scheme – Phase I Nebbi District
  • Intake Works on of River Nyarwodho Erussi Sub County.
  • 5.2km Raw Water Gravity Main to Treatment Works in OD 250mm uPVC and DN 250 steel for sections above ground
  • 4,000m3/d Water Treatment Works at Kei Village, Erussi Sub County comprising coagulation, flocculation, sedimentation, rapid gravity filtration and disinfection
  • 32.3km Treated Water Transmission mains of OD 280 – 110mm uPVC pipelines with 3no. 10m3 Break-Pressure Tanks
  • Storage Pressed steel tanks at Oweko 31m3, Nyaravur 158m3 and Goti-Madi 222m3
  • Distribution Mains:
    40.2km of Primary distribution lines in OD 40 – OD 90 HDPE and 15.2 km of OD 110 – OD 250 uPVC
    55.7km of Secondary distributions
  • Consumer Connections: 730 water points installed at household level.
  • Town Office Block: 80m2 Office blocks at Nyaravur and Alwi
2014-2017 Min of Water & Environment Detailed Design and Reconstruction Supervision of Mabira Dam Mbarara district Mabira dam is an existing reservoir which was constructed way back in the 1940/50’s but first rehabilitated in 2003.

  • Design appropriate cost-effective water for production facility with structures for provision of water for Livestock watering, Irrigation and Domestic water uses.
  • Supervise and monitor the construction of the designed water for production facility to ensure efficiency and value of money.
  • Assist the Client in the Tendering process.
  • Develop a strategy for mobilizing and organising local authorities and user communities for post-construction operation and maintenance.